Hexloom LabsKits
Published 2026-10-05 · sources checked 2026-10-05

Renovation budget by room spreadsheet: SUMIFS per room, with an overrun flag

A room-by-room budget is one table of scope lines with a Room column, plus a summary that uses SUMIFS to total each room. Here is a five-room example with a flag for any room more than 10% over its budget.

Free: Contingency & Change Order Tracker, one Excel tab. Confirm your email and the file arrives right away, plus an occasional note (at most one a week) on keeping a renovation on budget. Unsubscribe in one click. Privacy.

General information only, not financial, construction or legal advice. Contingency, holdback and payment-split percentages are your own inputs, and payment and deposit rules vary by contract and by state or province; check yours. Figures cited from other sources are dated where they appear.

One table of lines, one summary by room

A renovation budget by room does not need a sheet per room. It can be a single table with one row per scope line and a Room column, plus a summary that uses SUMIFS to total each room. Adding a sixth room later means adding a name to the room list, not building another sheet. Below is a five-room example, the formulas to rebuild it, and a flag for any room more than 10% over its budget. The 10% is a threshold you type, not a rule.

The lines table

Put the scope lines on one sheet, called Lines here, with headers in row 1 and data from row 2. A layout to rebuild: A Line ID, B Room, C Item, D Category, E Contractor, F Budget, G Base quote, H Approved COs, I Committed, J Paid, K Remaining, L Flag.

I2  Committed   =G2+H2
K2  Remaining   =F2-I2
L2  Flag        =IF(J2>I2,"Overpaid",IF(I2>F2,"Over budget",IF(I2=0,"Not committed","OK")))

Worked example: five rooms

Room-level figures after rolling the lines up. Remaining is Budget minus Committed. Over or under is (Committed - Budget) divided by Budget, rounded to one decimal.

RoomBudgetCommittedPaidRemainingOver or underFlag at 10%
Kitchen$40,000$41,600$12,400-$1,600+4.0%OK
Primary bath$22,000$18,500$6,000$3,500-15.9%OK
Hall bath$9,000$10,200$3,000-$1,200+13.3%Check
Living room$7,500$7,200$2,400$300-4.0%OK
Mudroom$4,500$4,950$1,500-$450+10.0%OK
Total$83,000$82,450$25,300$550-0.7%

The project as a whole is $550 under budget, and three rooms are over their own. That is why the room view exists: a total can look fine while one room is not. Only the hall bath is flagged, because $1,200 over on $9,000 is 13.3%. The mudroom is $450 over, exactly 10.0%, and the flag asks for more than 10%, so it stays OK. If you want that room flagged, set the threshold to 9% or switch to a greater-than-or-equal test.

Drill into the flagged room

A room flag tells you where to look, not why. Filter the Lines sheet to Hall bath and the cause is on the page:

LineBudgetCommittedOver byOver by %
Tile$3,000$3,600$60020.0%
Plumbing$2,500$2,800$30012.0%
Vanity$1,800$1,900$1005.6%
Paint and trim$1,700$1,900$20011.8%
Hall bath$9,000$10,200$1,20013.3%

All four lines are over, and tile alone is half of the $1,200. That points the next conversation at one quote rather than at the whole room.

The summary formulas

On a Summary sheet: rooms in A5 to A9, the threshold in B2 (type 10%), headers in row 4.

B5  Budget       =SUMIFS(Lines!$F$2:$F$200,Lines!$B$2:$B$200,$A5)
C5  Committed    =SUMIFS(Lines!$I$2:$I$200,Lines!$B$2:$B$200,$A5)
D5  Paid         =SUMIFS(Lines!$J$2:$J$200,Lines!$B$2:$B$200,$A5)
E5  Remaining    =B5-C5
F5  Over/under   =IF(B5=0,0,ROUND((C5-B5)/B5,4))
G5  Flag         =IF(F5>$B$2,"Check","OK")

Totals (row 10)  =SUM(B5:B9)   =SUM(C5:C9)   =SUM(D5:D9)
Project over/under  =IF(B10=0,0,ROUND((C10-B10)/B10,4))

Room by category  =SUMIFS(Lines!$F$2:$F$200,Lines!$B$2:$B$200,$A5,Lines!$D$2:$D$200,"Tile")
Lines in the room =COUNTIFS(Lines!$B$2:$B$200,$A5)
Lines over budget =COUNTIFS(Lines!$B$2:$B$200,$A5,Lines!$L$2:$L$200,"Over budget")

Tie-out           =SUM(Lines!$F$2:$F$200)-B10

The ROUND to four decimals (a percentage to two places) stops a value such as 0.1000000001 from tipping a boundary case the wrong way, which matters for a room sitting exactly on the threshold. The ranges run to row 200 so new lines are picked up without editing the formulas.

Checks that catch the usual errors

Where to go next

For the budget-versus-quote side of each line, see committed versus paid. For single-room versions of the same method, see the kitchen and bathroom guides. If the money in a room moves through several trades, the payment schedule guide covers when each payment falls due.

What this does not do

This is a planning tool, not financial, construction or legal advice. It adds up the figures you enter and compares them with the budgets you set; it does not estimate costs or decide whether a room is on track, and the 10% flag is your input. It says nothing about taxes. The Hexloom Renovation Budget Tracker keeps the room list, scope lines and per-room totals in one Excel file.

More renovation budget guides

Already built

The Budget tab of the Hexloom Renovation Budget Tracker has one row per scope line with a room picked from the room list on Start Here. The Rooms & Summary tab totals Budget, Committed, Paid and Remaining for each room and for each category, and shows the overall variance % and the count of lines flagged Over budget or Not committed. It is one Excel file, $29 one time, with no bank link and no account.

See what is inside