Renovation contingency tracker: how much contingency is left

A contingency fund is only useful if you can see how much of it is gone. This page shows the pool, used and left calculations in Excel, with a $60,000 example at 15%.

Free: Contingency & Change Order Tracker, one Excel tab. Confirm your email and the file arrives right away, plus an occasional note (at most one a week) on keeping a renovation on budget. Unsubscribe in one click. Privacy.

General information only, not financial, construction or legal advice. Contingency, holdback and payment-split percentages are your own inputs, and payment and deposit rules vary by contract and by state or province; check yours. Figures cited from other sources are dated where they appear.

The answer in one line

Contingency left is the pool minus what has already been used, and the pool is your total budget times your contingency percentage. Show it twice: left now (approved changes only) and left if pending is approved. On a $60,000 project with a 15% contingency, the pool is $9,000. With $3,550 used and $1,800 pending, $5,450 is left now and $3,650 if the pending item is approved.

The pool sits inside the total

The pool is held inside the total budget, not added on top. Here $60,000 at 15% is a $9,000 pool, so the scope lines carry $51,000 between them. Count the pool as extra money on top of the lines and the sheet shows room that does not exist.

There is no single right percentage. As of 2026-10-05, one contractor's budgeting guide says: "Most renovation professionals recommend reserving 10% to 20% of your total project budget as a contingency fund" (Crosspoint Contracting). Another says: "Most experts suggest you save 10 to 15 percent of your total project cost for extras", and to aim for the higher end if the home is more than 30 years old (Levelworks). The two ranges differ, which is the point: this example uses 15% as an input, and you set your own.

Worked example: six lines, two overruns, one pending change

Used means committed above a line's own budget, summed line by line. Put headings in row 1 and the lines in rows 2 to 7.

A: LineB: ItemC: BudgetD: CommittedE: OverrunNote
L01Demolition and framing$9,500$9,500$0
L02Plumbing$8,000$8,000$0
L03Cabinets$14,000$16,400$2,400CO#1 approved, +2,400
L04Electrical$6,000$7,150$1,150CO#2 approved, +1,150
L05Tile$9,500$9,500$0
L06Paint and trim$4,000$4,000$0CO#3 proposed, +1,800
Total$51,000$54,550$3,550
ResultWorkingValue
Pool60,000 x 15%$9,000
Used2,400 + 1,150$3,550
Left now9,000 - 3,550$5,450
Pending exposureCO#3$1,800
Left if pending is approved5,450 - 1,800$3,650
Pool used now3,550 / 9,00039.4%
Pool used if pending is approved5,350 / 9,00059.4%

Percentages are rounded to one decimal. As a cross-check, the lines are committed at $54,550 against a $60,000 total, which also leaves $5,450. That match holds here because every other line is committed at exactly its budget; a line that finishes under budget would make the two numbers differ.

The formulas

The per-line table sits in A to E and the summary in G and H, so they do not overlap.

E2   Overrun per line   =MAX(0,D2-C2)          (fill down rows 2-7)

H1   Total budget       60000   (typed)
H2   Contingency %      15%     (typed)
H3   Pool               =H1*H2                              9,000
H4   Lines should total =H1-H3                              51,000
H5   Lines check        =SUM(C2:C7)-H4                      0
H6   Used               =SUM(E2:E7)                         3,550
H7   Left now           =H3-H6                              5,450
H8   Pending exposure   =SUMIFS('Change Orders'!$F$2:$F$100,'Change Orders'!$G$2:$G$100,"Proposed")   1,800
H9   Left if approved   =H7-H8                              3,650
H10  Pool used %        =IF(H3=0,0,H6/H3)                   39.4%
H11  If approved %      =IF(H3=0,0,(H6+H8)/H3)              59.4%

H5 guards against counting the pool twice: if the line budgets do not add up to the total minus the pool, it will not read 0. A negative H7 means used has gone past the pool, and the overspend is coming out of other lines' room.

H8 is the cautious reading. A proposed change on a line with unspent budget might not touch the pool at all, but the sheet cannot know that, so it treats the whole amount as exposure.

Reading the result

Compare the share of the pool used with how much of the work is done. The same 39.4% means something different when demolition has just finished than when only paint is left. That comparison is your judgment; the sheet only supplies the first number.

Mistakes and checks

Related guides

The overruns come from approved change orders, logged as in the change order tracker guide; Committed is explained in committed vs paid. For a small bathroom where the pool changes how much looks left, see the bathroom remodel budget spreadsheet. The Hexloom Renovation Budget Tracker shows pool, used and left on one summary tab.

What this does not do

This is a planning tool, not financial, construction or legal advice. It does not recommend a contingency percentage; 15% is the example's own input and the published ranges above are what two sources state, not guidance for your house. It does not predict what you will find behind a wall.

Sources

More renovation budget guides

Already built

On the Start Here tab of the Hexloom Renovation Budget Tracker you enter the total budget and contingency percentage, and the Rooms & Summary tab shows the contingency pool, used and left. Used is the sum of overruns, meaning Committed above a line's Budget, taken from the Budget tab. The Change Orders tab adds pending exposure so you can see what is left if proposed changes pass. It is one Excel file, $29 one time, with no bank link and no account.

See what is inside